The procurement entails the design, manufacturing, delivery, installation, and commissioning of a Proton
Exchange Membrane (PEM) electrolysis system f...
or hydrogen production at the JRC Ispra site. The core of the system
is a 50 Nm3/h electrolyser (which must be upgradable to 100 Nm3/h) that delivers hydrogen at an outlet pressure
of 30 barg. The main equipment will be delivered in a containerized
🔓 Sign up free to read the full description and browse 100,000+ open tenders
Get instant access to complete tender details, deadlines, and AI-powered matching.
Create Free AccountAlready have an account? Sign in
The procurement entails the design, manufacturing, delivery, installation, and commissioning of a Proton
Exchange Membrane (PEM) electrolysis system for hydrogen production at the JRC Ispra site. The core of the system
is a 50 Nm3/h electrolyser (which must be upgradable to 100 Nm3/h) that delivers hydrogen at an outlet pressure
of 30 barg. The main equipment will be delivered in a containerized/skid version divided into three specific areas:
a control panel area with the AC/DC converter, a water purification unit, and an ATEXclassified area containing
the stacks and gas purification treatment. In addition to the containerized unit, the scope of supply includes several
external components: An MV/LV transformer A thermal management system (dry cooler) A lowpressure hydrogen
storage system consisting of a cylinder rack at 30 bar with a total volume of 5 m3 A gas blender installed on the
outlet piping after the storage Finally, the procurement includes a comprehensive service package covering the
Factory Acceptance Test (FAT), Site Acceptance Test (SAT), ATEX verification, staff training, two years of spare parts,
and a 3year maintenance contract. Reason for Purchasing The primary objective of this procurement is to produce
green hydrogen by harnessing the renewable energy generated from the JRC Ispra site's internal photovoltaic (PV)
plant. Currently, the site has a 1.35 MWp PV installation, which is planned to be expanded to 2 MWp and eventually
3 MWp in the future. Instead of using battery systems, the JRC intends to use the excess energy from this PV plant
to power the electrolyser for selfconsumption. The hydrogen produced will then be blended into the natural gas
pipeline (up to a 10% volume blend) to feed the site's cogenerators. A dedicated technical sizing analysis concluded
that a modular 2x250 kW electrolyser is the optimal choice, as it offers the best compromise between the available
PV power, the number of operating hours, and the d